Scrum Agenda for a Sprint


Sprint Planning, Daily Scrum, Sprint Review and Sprint Retrospective are the Scrum's events inside a Sprint.

Figure 1 presents the Sprint events as they would happen during a two-weeks-time-box Sprint agenda.

For each event a time-box is provided that is relative to the two weeks Sprint.


Sprint Planning and Sprint Retrospective requires the Scrum Team presence (PO, SM, DT), while only the Development Team needs to attend the Daily Scrum.

The Scrum Team plus the relevant Stakeholders partecipate to the Sprint Review.


Figure 1



For integrity here below the time-boxes for a 1-month Sprint.


Sprint Planning: 4 hours

Daily Scrum: 15 minutes

Sprint Review: 4 hours

Sprint Retrospective: 3 hours



©Maxieweb